Installed Generation Capacity
THERMAL | ||
---|---|---|
Constituent | Power Plant | Installed Capacity in MW |
WBPDCL | BTPS | 4X60+210=450 |
STPS | 2X250=500 | |
KTPS | 6X210=1260 | |
BkTPP | 5X210=1050 | |
SgTPP | 2X300=600 | |
CESC | BUDGE BUDGE | 3X250=750 |
TITAGARH | 4X60=240 | |
SOUTHERN GENERATING STATION | 2X67.5 | |
NEW COSSIPORE | 100 | |
DPL | DPL | |
HEL | HEL | 2X300=600 |
HYDEL | ||
Constituent | Power Plant | Installed Capacity in MW |
---|---|---|
WBSEDCL | PPSP | 4X225=900 |
RAMMUM | 4X12.75=51 | |
TCF | 9X7.5=64.5 | |
JALDHAKA | 2X4+4X9=44 | |
NHPC | TLDP PHASE-III | 4X33=132 |
OTHERS | ||
Constituent | Power Plant | Installed Capacity in MW |
TPCL | TPCL | 2X45+1X30=120 |
CPL | CPL | 40 |
PCBL | PCBL | 30 |
SIIPL | SIIPL | 5 |